A specification was changed early in your project, causing you to overspend a bit in the first
Fantastic news! We've Found the answer you've been seeking!
Question:
A specification was changed early in your project, causing you to overspend a bit in the first half. Your boss wants to know what the forecast costs will be at its completion. How should you proceed?
A Assume the project will underspend and be late in the second half.
B Assume the project will have the same amount of overspending and lateness in the second half.
C The overall costs will be increased unless the specification is reduced in another part of the project.
D Assume the project will be over budget and deliver early.