Question: A SPI ( schedule performance index ) value less than 1 indicates that the project is: a . Behind the schedule b . Ahead of

A SPI (schedule performance index) value less than 1 indicates that the project is:
a. Behind the schedule
b. Ahead of schedule
c. Over budgeted
d. Under budget
 A SPI (schedule performance index) value less than 1 indicates that