Question: Task Build forms Pour foundation Pour foundation Frame walls Frame walls Shingle roof Install siding Install electrical and plumbing Finish carpentry Month April April May

Task Build forms Pour foundation Pour foundation

Task Build forms Pour foundation Pour foundation Frame walls Frame walls Shingle roof Install siding Install electrical and plumbing Finish carpentry Month April April May June July July July August September Budgeted Amount $10,000 $50,000 $100,000 $30,000 $30,000 $60,000 $50,000 $100,000 $140,000 Define each term below in your own words and calculate these values for the above project. Show your work: 5.1.4 Budgeted cost baseline (provide a definition and create a baseline graph using Excel) 5.1.5 Budget at Completion (BAC) 5.1.6 Planned Value (PV) as of the end of May 5.1.7 Earned Value (EV) if all of April's work is completed and only 50% of May's pour foundation is completed. 5.1.8 Schedule Variance (SV) as of the end of May using the above EV. Is this good or bad? 5.1.9 Cost Variance (CV) as of the end of May if Actual Cost (AC) at the end of May is $100,000. Is this good or bad? 5.1.10 Schedule Performance Index (SPI). Explain what it indicates for this project. 5.1.11 Cost Performance Index (CPI). Explain what it indicates for this project. 5.1.12 Estimate to Complete (ETC), assuming that the previous cost variances will not affect future costs 5.1.13 Estimate at completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!