Question: A stakeholder is requesting project status daily but has no decision - making responsibilities on the project. How would you classify this stakeholder on the

A stakeholder is requesting project status daily but has no decision-making responsibilities on the project. How would you classify this stakeholder on the
power and interest grid?
A
Keep informed