Question: A standard procedure for numerically measuring a project's progress, forecasting its completion date and cost and providing measures of schedule and budget variation as activities

A standard procedure for numerically measuring a project's progress, forecasting its completion date and cost and providing measures of schedule and budget variation as activities are completed is referred to as
program evaluation and review technique (PERT)
16
the critical path method (CPM)
a Gantt chart
earned value analysis (EVA)
 A standard procedure for numerically measuring a project's progress, forecasting its