Question: A stipulation from Senior Management that a design does not have to be fully complete before manufacturing some components can start is an example of
A stipulation from Senior Management that a design does not have to be fully complete before manufacturing some components can start is an example of a:
a. crashing
b. scope dependency
c. discretionary dependency
d. fast tracking