Question: A stipulation from Senior Management that a design must be fully complete before manufacturing can start is an example of a: a. external dependency b.
A stipulation from Senior Management that a design must be fully complete before manufacturing can start is an example of a:
| a. | external dependency | |
| b. | scope dependency | |
| c. | discretionary dependency | |
| d. | mandatory dependency |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts