Question: A structural fill project requires a compaction to a density of 1 9 8 0 kg / m 3 at a water content of 1

A structural fill project requires a compaction to a density of 1980 kg/m3 at a
water content of 11.4%. The specific gravity of the soil particles is 2.66. The
specifications require that the void ratio not exceed 0.80 with the compaction. Has
the specification been met?