Question: A student has 6 projects to complete. The due dates and processing times are presented below Class Project Due Date Processing Time 15 10 1

A student has 6 projects to complete. The due dates and processing times are presented below Class Project Due Date Processing Time 15 10 1 2 6 3 3 9 4 4 12 8 5 20 10 6 30 6 If EDD, . the sequence of jobs is Select)