Question: A student has 6 projects to complete. The due dates and processing times are presented below Class Project Due Date Processing Time 1 15 10

A student has 6 projects to complete. The dueA student has 6 projects to complete. The due

A student has 6 projects to complete. The due dates and processing times are presented below Class Project Due Date Processing Time 1 15 10 N 6. 3 3 9 4 4 12 8 5 20 10 6 6 30 6 If MH-Algorithm, > the sequence of jobs is [Select] > the number of tardy jobs is [Select] The makespan is [Select]