Question: A student wants to schedule a project using PERT. The network diagram is drawn in AOA format (activity on arrow). She has determined the following
A student wants to schedule a project using PERT. The network diagram is drawn in AOA format (activity on arrow). She has determined the following activities, precedence relationships and time estimates in days for the project:
TIME estimate Exp Time
Act to tm tp te
a 4 6 7 5.83
b 1 2 3 2.00
c 5 5 5 5.00
d 7 9 12 9.17
e 2 4 8 4.33
f 6 9 10 8.67
1-a. Name all potential paths and corresponding durations
1-b. Calculate ES, EF, LS, LF, and slack for all activities.
1-c. How many days can activity "c" be delayed without extending project duration?
1-d. If activity "f" is delayed by 2 days, by haw many days will it extend project duration?