Question: 2 . A student wants to develop a project using PERT to modify one of products which has poor sales. She has determined the following

2. A student wants to develop a project using PERT to modify one of products which has poor sales. She has determined the following activities, precedence relationships and time estimates in days for the project:
TIME estimate Exp Time Variance
Act to tm tp te Vt
a 4675.830.250
b 1232.000.111
c 5555.000.000
d 79129.170.694
e 2484.331.000
f 69108.670.444
a) Name all potential paths and corresponding durations
b) Calculate ES, EF, LS, LF, and slack for all activities.
c) How many days can activity "e" be delayed without extending project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock