Question: - A subcontractor must do the following: a. Framing (5 days) b. Drywall installation ( 4 days) c. Drywall finish and paint ( 3 days)

 - A subcontractor must do the following: a. Framing (5 days)

- A subcontractor must do the following: a. Framing (5 days) b. Drywall installation ( 4 days) c. Drywall finish and paint ( 3 days) - Assuming he wants to make sure each activity finishes as least 1 day after its predecessor has finished, draw these three activities in a precedence diagram and calculate how much time the subcontractor would need to finish all three activities