Question: A subcontractor must do the following: a. Framing (5 days) b. Drywall installation (4 days) c. Drywall finish and paint (3 days) Assuming he wants
A subcontractor must do the following:
a. Framing (5 days)
b. Drywall installation (4 days)
c. Drywall finish and paint (3 days)
Assuming he wants to make sure each activity finishes as least 1 day after its predecessor has finished, draw these three activities in a precedence diagram and calculate how much time the subcontractor would need to finish all three activities.