Question: A summary task should be at a higher outline level in your project. What technique would you use to correct this? Right click the summary
A summary task should be at a higher outline level in your project. What technique would you use to correct this?
Right click the summary task and choose "set to higher level" from the choices on the menu.
Outdent the summary task.
Drag the summary task to a level higher than its current status
Indent the summary task.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock