Question: A system has four processes and five different types of resources. The current allocation and maximum needs are follows: Allocated Process A 1 0 0

A system has four processes and five different types of resources. The
current allocation and maximum needs are follows:
Allocated
Process A 100211
Process B 20111
Process C 11010
Process D 111110
Maximum
11213
The available resources after allocation are
Available =[01212]. What is the largest
possible value of x so that ADBC is a saf
sequence? In order to get credits, you should
2211
show your work clearly!
21310
11221
 A system has four processes and five different types of resources.