Question: A system has four processes and five different types of resources. The current allocation and maximum needs are follows: Allocated Maximum Process A 1021111213 Process

A system has four processes and five different types of resources. The current allocation and maximum needs are follows: Allocated Maximum Process A 1021111213 Process B 2011122 X 11 Process C 11010 2 1310 Process D 1111011221 The available resources after allocation are available= [ 0 0 2 1 1]. What is the largest possible value of X so that DCBA is a safe sequence? In order to get credits, you should show your work clearly