Question: A system has three components and requires all three to be operational during 7 a.m. to 3 p.m. business hours, Sunday through Friday. Failure of
A system has three components and requires all three to be operational during 7 a.m. to 3 p.m. business hours, Sunday through Friday. Failure of component 2 occurs as follows:
Sunday = 7 a.m. to 11 a.m.
Monday = 8 a.m. to 11 a.m.
Tuesday = No failure
Wednesday = 3 p.m. to 7 p.m.
Thursday = 5 p.m. to 8 p.m.
Friday = 1 p.m. to 2 p.m.
Saturday = No failure
Calculate the availability of component 2.