A company has three components in a system and requires all three to be operational for 24 hours, Monday to Friday. The failure of component 1 occurs as follows:
Monday = No failure
Tuesday = 5 a.m. to 7 a.m.
Wednesday = No failure
Thursday = 4 p.m. to 8 p.m.
Friday = 8 a.m. to 11 a.m.
Calculate the MTBF and MTTR of component 1.