Question: A system to be designed and implemented is counted as comprising 3 3 0 0 FPs . What would be the total charge according to
A system to be designed and implemented is counted as comprising FPs What would be the total charge according to the schedule given in the below table ii A contract stipulates that a computer application is to be designed, constructed, and delivered at a cost of Rs per FP After acceptance testing, the customer asks for changes to some of the functions in the system amounting
FPs
and some new functions which amount to additional FPs Using the below table calculate the additional charge.