Question: A . Task A and Task B are q , tasks, meaning they can be started at the same time. parallel critical serial B .
A Task A and Task B are tasks, meaning they can be started at the same time.
parallel
critical
serial
B Which path is the critical path?
ACFH
ADF
BEG
ADFH
ACF
C What is the duration of the critical path in this network diagram?
weeks
D If task takes weeks instead of weeks to finish, what effect will it have on the overall project duration?
Increases project duration by weeks.
No effect on project duration because task has slack of weeks Decreases project duration by weeks.
E Complete a forward pass on the network diagram. What is the early start for task F weeks
F Complete a backward pass on the network diagram. What is the late finish for task I?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
