Question: A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. The

A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. The expected task duration is: A. 10 days B. 12 days C. 11.5 days D. 11 days E. 10