Question: A task has an optimistic completion time of 7 days, a most likely completion time of 1 0 days, and a pessimistic completion time of

A task has an optimistic completion time of 7 days, a most likely completion time of 10 days, and a pessimistic completion time of 13 days. What is the expected completion time of 13 days? What is the variance of the tasks completion time?