Question: QUESTION 2 9 A task has an optimistic completion time of 4 days, a most likely time of 1 0 days, and a pessimistic time

QUESTION 29
A task has an optimistic completion time of 4 days, a most likely time of 10 days, and a pessimistic time of 13 days. The expected task duration is:
A.10.5 days
B.10 days
C.12 days
D.11 days
E.11.5 days