Question: A task has been completed 30% against scheduled 50%. The budgeted cost of task is Rs 5000. Amount actually spent is Rs 2000. CPI is
A task has been completed 30% against scheduled 50%. The budgeted cost of task is Rs 5000. Amount actually spent is Rs 2000. CPI is