Question: A task involves positioning two metal parts with a rubber gasket sandwiched between them, inserting two bolts into pre-drilled holes, threading a nut onto each

A task involves positioning two metal parts with a rubber gasket sandwiched between them, inserting two bolts into pre-drilled holes, threading a nut onto each bolt, and tightening each bolt with a pneumatic wrench. In a preliminary study, the manager observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.

Observation:

1

2

3

4

5

Average time

Normal time

Standard time

Task time (seconds):

50

54

60

145

56

X

Y

Z

What is the standard time " Z " for this task, if the employee worked at a 10% slower rate than typical for adequately trained workers and her allowance is 14%? (Hint: compute X, Y and Z, in that order).

A.

76.4

B.

65.3

C.

99.6

D.

99.2

E.

110.9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!