Question: A team decides that an agile approach fits the needs of the next phase in their project. Unfortunately, some team members have not had the
A team decides that an agile approach fits the needs of the next phase in their project. Unfortunately, some team members have not had the appropriate agile training. How should the project manager respond to the lack of agile training?
Group of answer choices
Ensure the projects contingency reserve can cover agile training for all team members.
Create virtual training sessions for key team members, covering the main agile topics.
Transition some of these team members to other teams and replace them with resources with agile training.
Identify and implement the most costeffective agile training for the team members.