Question: A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool

A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate? a. matrix diagram b. cause-and-effect diagram c. process decision program chart d. affinity diagram e. activity network diagram f. tree diagram g. prioritization matrix h. matrix diagram I. Interrelationship diagraph