Question: a) The 1st unit = ___ hours (round to two decimals) b) The 8th unit = ___ hours (round to two decimals) c) The total
a) The 1st unit = ___ hours (round to two decimals)
Girish Shambu and William Reisel are teammates at a discount store, their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 90%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for
b) The 8th unit = ___ hours (round to two decimals)
c) The total amount of hours to build the 8 units = _____ hours (round to two decimal places)