Question: a) The activity shown in Table Q1 (a) are processes carried out in a manufacturing company. Based on the table provided, (1) (11) Determine the
a) The activity shown in Table Q1 (a) are processes carried out in a manufacturing company. Based on the table provided, (1) (11) Determine the Critical Path and Project Duration to complete the process. Activity E cannot start immediately after activity C. The delay is expected to be 5 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process. Table Q1 (a) Activity Processes A B D E F G H I J K Customer order Service department Raw material store QA inspection of material Parts fabrication Test parts Modules assembly Inspect module assembly Fix faulty modules Assembly Fix faulty product Predecessor Duration (Days) 1 3 6 B 3 5 4 EF 7 A 6 3 HI 10 D G J 2