Question: a) The expected (estimated) time for activity C is 12.5 weeks. b) The variance for activity C is 2.25 weeks. c) Based on the calculation

a) The expected (estimated) time for activity C is 12.5 weeks.

b) The variance for activity C is 2.25 weeks.

c) Based on the calculation of the estimated times, the critical path is A - C - F - H - J - K .

d) The estimated time for the critical path is 41.17 weeks. (Round your response to two decimal places.)

e) The activity variance along the critical path is 10.96 weeks. (Round your response to two decimal places.)

f) Using the standard normal table .. , the probability that Hopkins Hospitality will finish the project in 42 weeks or less is nothing . (Enter as a probability and round your response to three decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!