Question: a) The expected (estimated) time for activity C is ____________. (Round your response to two decimal places.) b) The variance for activity C is ___________(Round
a) The expected (estimated) time for activity C is ____________. (Round your response to two decimal places.)
b) The variance for activity C is ___________(Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is _____________.
.
d) The estimated time for the critical path is _____________weeks. (Round your response to two decimalplaces.)
e) The activity variance along the critical path is ______________weeks. (Round your response to two decimalplaces.)
f) The probability that Hopkins Hospitality will finish the project in 36 weeks or less is ________________. (Enter as a probability and round your response to three decimalplaces.)
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels