Question: A) The expected (estimated) time for activity C is ___ weeks. (Round your response to two decimal places.) B) The variance for activity C is

A) The expected (estimated) time for activity C is ___ weeks. (Round your response to two decimal places.)

B) The variance for activity C is ___ weeks. (Round your response to two decimal places.)

C) Based on the calculation of the estimated times, the critical path is__

D) The estimated time for the critical path is ____weeks. (Round your response to two decimal places.)

E) The activity variance along the critical path is ___ weeks. (Round your response to two decimal places.)

F) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 40 weeks or less is ___ (Enter as a probability and round your response to three decimal places.)

A) The expected (estimated) time for activity C

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Time (weeks) a m b Immediate Predecessor(s) a m b Activity A Activity G Immediate Predecessor(s) C, E 4 8 3 3 5 2 8 10 24 16 A 1 1 1 9 12 A UI - DV 7 7 7 4 7 9 4 12 7 3 D, G, H I, J 1 2 B 3 4 4 21 5 9 C, E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!