Question: a) The information in Table 2 is available about a large project. Construct the network diagram for this project. Determine the project's critical path and

a) The information in Table 2 is available about

a) The information in Table 2 is available about a large project. Construct the network diagram for this project. Determine the project's critical path and highlight it together with the duration of the expected completion time for the project. Do include slacks for each node. Table 2 Activity Immediate Predecessor(s) A B D E F G H I J K L M N 0 Activity Time (days) 3 4 2 5 3 4 6 2 1 4 3 3 2 4 1 5 A B B CD C.D.E E D.E F G GHI 1.J K.M H.M N.L.O