Question: a) The information necessary for the Program Evaluation and Review Technique (PERT) analysis of a project is given in the following table. The project's data

a) The information necessary for the Program Evaluation and Review Technique (PERT) analysis of a project is given in the following table. The project's data for Q1-a. Activity A B C D E F G H I JK Predecessors B, CB,C DE DE H F.GGI 53 3 1-3 5 1 1 3 1 1 5 Duration m 8 12 T 8 1 - 0 3 1 2 8 (Weeks) b17 15 T+3 23 1 13 9 11 1 2 11 a 1 2 What is the minimum value of "T" that makes activity C a critical activity? [10 Marks]