Question: a) The information necessary for the Program Evaluation and Review Technique (PERT) analysis of a project is given in the following table. The project's data

a) The information necessary for the Program

a) The information necessary for the Program Evaluation and Review Technique (PERT) analysis of a project is given in the following table. The project's data for Q1-a. Activity A B C D E F G H I JK Predecessors B, CB,C DE DE H F.GGI 53 3 1-3 5 1 1 3 1 1 5 Duration m 8 12 T 8 1 - 0 3 1 2 8 (Weeks) b17 15 T+3 23 1 13 9 11 1 2 11 a 1 2 What is the minimum value of "T" that makes activity C a critical activity? [10 Marks]