Question: a) The normal time for the complete operation = nothing minutes (round your response to two decimal places). b.) calculate the standard time answer both

a) The normal time for the complete operation = nothing minutes (round your response to two decimal places).
b.) calculate the standard time
answer both parts to this question please
Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 5 0.6 Performance Rating 115% 90% 85% 80% 1 2 3 4 Observation (minutes per cycle) 2 3 4 0.5 0.7 0.3 0.7 0.6 0.5 0.4 0.7 0.4 1.7 2.0 1.8 0.5 0.5 0.6 0.4 1.5 0.5 1.6 The allowances for tasks such as this are personal, 6%; fatigue, 10%; and delay, 3%. a) The normal time for the complete operation = minutes (round your response to two decimal places)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts