Question: a. This question relates to a new project.It has an expected completion time of 25 weeks and a variance of 3.88. The deadline for the
a. This question relates to a new project.It has an expected completion time of 25 weeks and a variance of 3.88.
The deadline for the project is 28 weeks.What is the probability of finishing on time?Express as a percentage with one decimal place (i.e. 65.2)
b. This question relates to a new project.It has an expected completion time of 25 weeks and a variance of 3.88.
The deadline for the project is 28 weeks.What is the probability of finishing late?Express as a percentage with one decimal place (i.e. 65.2).
c. This question relates to a new project.It has an expected completion time of 25 weeks and a variance of 3.88.
What is the probability of finishing the project in 24 weeks?Express as a percentage with one decimal place (i.e. 65.2).