Question: A time study analyst observed a repetitive work cycle performed by a worker and then studied the task using a predetermined motion time system. During
A time study analyst observed a repetitive work cycle performed by a worker and then studied the task using a predetermined motion time system. During the observation, the analyst made a record of the work elements. He also made a note of the workers performance and rated it as 85%. Back in the office, the analyst listed the basic motion elements for the task and retrieved from his computer the corresponding normal time values. The sum of the normal times for the basic motion elements was 1.38 min. The company uses a PFD allowance factor of 15%. Determine the standard time for the task.