Question: A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the
A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table.
| OBSERVATIONS (minutes per cycle) | ||||||||||||||||
| Element | Performance Rating | 1 | 2 | 3 | 4 | 5 | 6 | |||||||||
| 1 | 90 | % | 0.37 | 0.42 | 0.32 | 0.32 | 0.32 | 0.32 | ||||||||
| 2 | 85 | 1.37 | 1.37 | 1.32 | 1.32 | 1.32 | 1.37 | |||||||||
| 3 | 110 | 0.72 | 0.72 | 0.62 | 0.67 | 0.72 | 0.67 | |||||||||
| 4 | 95 | 0.97 | 1.02 | 0.97 | 1.02 | 1.02 | 1.07 | |||||||||
a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.)
b. Find the normal time for each element. (Round your answers to 3 decimal places.)
c. Assuming an allowance factor of 7 percent of job time, compute the standard time for this job. (Round your answers to 3 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock