Question: A top - down estimate usually is: Select one:a . Done early in the project life history, done on a global comparative cost basis and
A topdown estimate usually is:
Select one:a Done early in the project life history, done on a global comparative cost basis and does not use a comprehensive WBS
b Done late in the project life history, done on a global comparative cost basis and uses a comprehensive WBS
c Done early in the project life history, done on a global comparative cost basis and uses a comprehensive WBS
d Done late in the project life history, done on a global comparative cost basis and does not use a comprehensive WBS