Question: a. Total Slack LE EF IS ES 7. Given the following Project Scheduling Problem (see table below) Draw the network model b. Solve the problem

a. Total Slack LE EF IS ES 7. Given the following
a. Total Slack LE EF IS ES 7. Given the following Project Scheduling Problem (see table below) Draw the network model b. Solve the problem 1. Complete the table ii. Find the Longest Span and the Critical Path Activity Immediate Time in Predecessors Weeks A None 5 B None 4 C None 8 D BC 4 E B. 12 F B 10 G A, E 3 H 2 I G H