Question: A tracking Gantt chart: Incorrect Response A ) Identifies the performance to budget for the overall project by a certain date. B ) Monitors costs

A tracking Gantt chart:
Incorrect Response
A)
Identifies the performance to budget for the overall project by a certain date.
B)
Monitors costs and budget expenditures.
Correct Answer
C)
Identifies the stage of completion for each task.
D)
Identifies key points in the project's progress.