Question: A tracking Gantt compares? Question 2 6 Select one: a . The baseline schedule to actual progress b . The baseline schedule to the original

A tracking Gantt compares?
Question 26Select one:
a.
The baseline schedule to actual progress
b.
The baseline schedule to the original plan
c.
The baseline schedule to budget variances
d.
The baseline schedule to corrective actions