Question: A traditional PERT analysis ( i . e . , based only on critical path ) for a project with multiple paths found the project

A traditional PERT analysis (i.e., based only on critical path) for a project with multiple paths found the project duration mean of 100 days with variance of 20. The standard deviation of individual activities in all parallel paths is about 10% of the respective means. A Monte Carlo simulation was carried out for the same project. Which of the following could be the mean and variance respectively generated for the project via simulation:
A.
90 and 12
B.
110 and 12
C.
110 and 25
D.
90 and 25