Question: A traditional PERT analysis ( i . e . , based only on critical path ) for a project with multiple paths found the project
A traditional PERT analysis ie based only on critical path for a project with multiple paths found the project duration mean of days with variance of The standard deviation of individual activities in all parallel paths is about of the respective means. A Monte Carlo simulation was carried out for the same project. Which of the following could be the mean and variance respectively generated for the project via simulation:
A
and
B
and
C
and
D
and