Question: A unique, one - time operational activity or effort is referred to as a project. a . True b . False A project team is
A unique, onetime operational activity or effort is referred to as a project.
a True
b False
A project team is typically crossfunctional in its make up
a True
b False
We calculate the LS and LF times in a CPMPERT network by using the forward pass
method.
a True
b False
Slack is the amount of time by which an activity can be delayed without delaying any of
the activities that follow it or the project as a whole.
a True
b False
Quality management and control are not a part of the project management process.
a True
b False
The critical path for a project is the shortest path through the project's network.
a True
b False
The objective of project crashing is to reduce project duration while maximize the cos
crashing
a True
b False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock