Question: a . Use two - pass method to determine the critical path ( you can show the different times in the above diagram if you
a Use twopass method to determine the critical path you can show the different times in
the above diagram if you like points
b What is the project duration? point
c What is the slack time of activity F point
d Activities A B C D can be crashed. The normal time, crash time, normal cost and crash cost
are shown in the table below. What is the daily crash cost of each activity? points
e The project needs to be completed in days. How can you achieve this goal at minimum
cost Please report your crashing steps in the table below. The table size does not imply
the number of steps that will be needed. points