Question: a Using Table 1 draw the network , find the critical path ,using CPM Set up the LP model TABLE 1 ACTIVITY Reduction Cost DURATION

a

Using Table 1 draw the network , find the critical path ,using CPM Set up the LP model

TABLE 1

ACTIVITY Reduction Cost DURATION
A - 10
B - 7
C A,B 5
D A,B 3
E C 4
F C,D 3
G F 14

b If we want to complete the project in 25 days , Set up LP model using Table 2

TABLE 2

ACTIVITY Reduction Cost Max Possible Reduction Time
A - 2
B - 2
C A,B 2
D A,B 2
E C 2
F C,D 2
G F 2

c If project due date is 30 , find the probability of project completion time at 30 days Using Table 3 with PERT

TABLE3

ACTIVITY Reduction Cost DURATION a b m
A - 10 8 12 10
B - 7 4 10 7
C A,B 5 4 6 5
D A,B 3 2 4 3
E C 4 2 6 4
F C,D 3 1 5 3
G F 14 8 20 14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!