Question: a Using Table 1 draw the network , find the critical path ,using CPM Set up the LP model TABLE 1 ACTIVITY Reduction Cost DURATION
a
Using Table 1 draw the network , find the critical path ,using CPM Set up the LP model
TABLE 1
| ACTIVITY | Reduction Cost | DURATION |
| A | - | 10 |
| B | - | 7 |
| C | A,B | 5 |
| D | A,B | 3 |
| E | C | 4 |
| F | C,D | 3 |
| G | F | 14 |
b If we want to complete the project in 25 days , Set up LP model using Table 2
TABLE 2
| ACTIVITY | Reduction Cost | Max Possible Reduction Time |
| A | - | 2 |
| B | - | 2 |
| C | A,B | 2 |
| D | A,B | 2 |
| E | C | 2 |
| F | C,D | 2 |
| G | F | 2 |
c If project due date is 30 , find the probability of project completion time at 30 days Using Table 3 with PERT
TABLE3
| ACTIVITY | Reduction Cost | DURATION | a | b | m |
| A | - | 10 | 8 | 12 | 10 |
| B | - | 7 | 4 | 10 | 7 |
| C | A,B | 5 | 4 | 6 | 5 |
| D | A,B | 3 | 2 | 4 | 3 |
| E | C | 4 | 2 | 6 | 4 |
| F | C,D | 3 | 1 | 5 | 3 |
| G | F | 14 | 8 | 20 | 14 |