Question: A . ) Using the data below, calculate the Crash Cost per week for each Activity. B . ) If you had to crash the

A.) Using the data below, calculate the Crash Cost per week for each Activity.
B.) If you had to crash the project by 5 days at the minimum cost, which Activites would you crash? What would the total crash cost be?
Time (Wks) Cost ($)
Activity Normal Crash Normal Crash Critial Path
A 4240007000 NO
B 5320004000 YES
C 2110001500 YES
D 6450009000 NO
E 3230005000 YES
F 4215003000 YES