Question: A. Using the data in Problem 5, determine the sequence Henri should follow if he uses the EDD (earliest due date) priority rule. B. Based
A. Using the data in Problem 5, determine the sequence Henri should follow if he uses
the EDD (earliest due date) priority rule.
B. Based on the sequence developed in part (a), calculate the following performance
measures: makespan, mean job flow time, average number of jobs in the system,
mean job lateness, mean job tardiness, and maximum tardiness

Henri's Custom Gowns has six jobs waiting to be processed. Each gown is at the beading work center. The job information is shown here. Henri has decided to try a different priority rule. Using the data in table, determine the sequence Henri should follow if he uses the EDD (earliest due date) priority rule. Job sequence